Supporting construction at a high-capacity nickel processing facility
Market
Petrochemical & Industrial
Key Services
Steel Erection
Tons
14,500Hillsdale Fabricators erected structural steel building modules for two process buildings at Vale’s nickel processing facility in Long Harbour, Newfoundland and Labrador, including the 263,000-square-foot Nickel/Cobalt Electrowinning building and the 182,000-square-foot Neutralization building.
As the modular plant build progressed, Hillsdale Fabricators erected 14,500 tons of structural steel to support installation of major equipment and long-span structures at the facility, designed to process 50,000 tons of nickel ore per year.

Key Facts
Nearly 445,000 SF of industrial building space
Large-scale modular construction